International Road, 5 KW after the monastery 70 KW solar plant

Contact us
  • home
  • International Road, 5 KW after the monastery 70 KW solar

Fawzy El-hossary

International Road, 5 KW after the monastery 70 KW solar plant

Identifying and assessing the location: September 31, 2019

Importing solar support structures: October 17, 2019

Deploying solar support structures: October 24, 2019

Installing the rest of plant: December 3, 2019

Building worker housing units: November 24, 2019


Challenge

March 31, 2020: Due to a complaint by Eng. Sobhy Shaheen regarding the weak water flow, we adjusted the following:

  • Voltage from 400 to 380
  • Number of motor turns from 1450 to 2950
  • MPPT from 500 to 450


Solution

Optimizing water flow to meet the client’s needs