Fawzy El-hossary
International Road, 5 KW after the monastery 70 KW solar plant
Identifying and assessing the location: September 31, 2019
Importing solar support structures: October 17, 2019
Deploying solar support structures: October 24, 2019
Installing the rest of plant: December 3, 2019
Building worker housing units: November 24, 2019
Challenge
March 31, 2020: Due to a complaint by Eng. Sobhy Shaheen regarding the weak water flow, we adjusted the following:
- Voltage from 400 to 380
- Number of motor turns from 1450 to 2950
- MPPT from 500 to 450
Solution
Optimizing water flow to meet the client’s needs